Case Study
Royal Entomological Society - A Case Study - the Bug Job
Amalgamated Lifts takes lift design and build to a new level with the delivery
of a totally custom built lift for the Royal Entomological Society
Headquarters.
Having relocated to new premises in the historic Mansion
House in St Albans the Society was keen to add a lift to
provide disabled visitors with access throughout the building
over its three floors. The Society houses research and
periodicals in a number of libraries and has many and
frequent visitors. From a technical and compliance
perspective both the engineering design and deployment
into a stairwell with the space constraints of this beautiful old
building was challenging. Absolutely no space around the outside of the lift car was
available and the lift had to extend into the eaves of the building roof. Amalgamated
Lifts' design engineering team utilised a direct acting hydraulic ram arrangement with
a bore hole to free up as much space as possible for the lift car. The unique design
meant the lift car and sling had to be custom built.
Computer modelling techniques were used to help the client envisage and agree the
finished look and feel of the completed lift The 8-person lift was specifically designed
to capture the essence of the Society, its internal walls are decorated with stunning
photography of a variety of insect life including ladybirds, mayflies and butterflies.
Very early on the project affectionately became known as 'the bug job'.
Few lift companies have the capability to design and implement a bespoke lift from
concept to completion; either because they don't have the design engineering skills or
relish the complexities of such projects. The biggest challenge initially was finding a
location for the lift. Having studied the building structurally, extensive surveys were
necessary to establish where the lift would fit and comply with legal requirements.
Using Solidworks software computer modelling techniques the designers were able to
find a site, with sufficient clearance, by taking the lift into the eaves of the building.
This meant demolishing a kitchen and opening up an old stairwell to create enough
space to accommodate the 8 person lift, the minimum lift size to comply with DDA
requirements. The design stage took about a month, where simplicity was paramount
in providing the most efficient solution possible.
Over the next three months a programme of extensive buildings works ensued. To
maximise the space available a direct-acting borehole hydraulic system was
implemented underneath the lift. While you would normally drill down to
accommodate the hydraulics the second challenge arose as it soon became evident
that the building was in fact sitting on almost solid granite. Impossible to drill, the only
option was to dig out the 2m wide by 3m deep pit by hand.
For sufficient clearance it was necessary to extend the lift shaft into the roof space,
which had to be fireproofed. Further building work involved supporting brickwork and
fitting an additional RSJ to existing shaft walls, building a new motor room in the
basement and providing support to the ground floor. A hole was cut in exterior walls to
put in the lift guides in through the shaft wall. New entrances were created on each
level of access, over three floors, and cosmetic modifications of the building were
made so that aesthetically it looked as if the lift had always been there.
The finishing touch was the inclusion of fantastic insect photography on the walls of
the lift car capturing the essence of the Society.
Finally ahead putting into service the lift was thoroughly tested in accordance with
EN81, Lifts Directive1995 requiring two days of testing to check all safety
components and devices all hydraulic system, valve, locks, buffers, safety gear, and
appropriate clearances to check not only that they work but the correct parts have
been installed.
The lift was completed on time and on budget. The whole project took 6 months and
was managed by Keith Stockbridge, Major Works Manager and was overseen by
Brian Appleby, Project Manager. Following building works two engineers installed the
hydraulics with additional engineers to fit out the lift cars. Amalgamated Lifts
continues to maintain the lift which hasn't had a single failure since commissioning -
we all like a happy ending.